Thank you to our 100th Celebration Sponsors...Join this amazing group- Columbia Bank, Wegmans of Hanover, Efficient Air Service, Kinnelon Veterinary Hospital, Party Connections, In Memory of Robert "Bob" Ferretti, Moxie Salon and Beauty Bar, Gimigliano, Mauriello & Maloney Law Group, Lakeside Bagels and Deli, Kinnelon Physical Therapy, Apple Montessori Schools, Gameday Sports, Kinnelon Soccer Club, Darmofalski Engineering, Kinnelon Youth Football Association, Cyndi Frank (Realtor), Scensy-Cyndi Frank (Director), Cindy Gallagher (Realtor), Thrive Orthodontics,In Memory of Jim Neill, Van Wageninger & Daughters Farms, LLC, Walter “Matt” Weiss, Realtor at KW Prosperity, Bella Events and Decor, Any Excuse for a Party!, Cronin, Hanley and Vanzile LLC. Terry O'Connor Realtors     
Thank you to our 100th Celebration Sponsors...Join this amazing group- Columbia Bank, Wegmans of Hanover, Efficient Air Service, Kinnelon Veterinary Hospital, Party Connections, In Memory of Robert "Bob" Ferretti, Moxie Salon and Beauty Bar, Gimigliano, Mauriello & Maloney Law Group, Lakeside Bagels and Deli, Kinnelon Physical Therapy, Apple Montessori Schools, Gameday Sports, Kinnelon Soccer Club, Darmofalski Engineering, Kinnelon Youth Football Association, Cyndi Frank (Realtor), Scensy-Cyndi Frank (Director), Cindy Gallagher (Realtor), Thrive Orthodontics,In Memory of Jim Neill, Van Wageninger & Daughters Farms, LLC, Walter “Matt” Weiss, Realtor at KW Prosperity, Bella Events and Decor, Any Excuse for a Party!, Cronin, Hanley and Vanzile LLC. Terry O'Connor Realtors     

News & Information

Silas Condict Park Entrance

Release Date: June 14, 2022
The Morris County Park Commission Engineer has provided an Update to the On-Going Entrance Road Repairs to Silas Condict Park.

The Morris County Park Commission Engineer has provided an Update to the On-Going Entrance Road Repairs to Silas Condict Park.

As of Monday, June 13th...

  • The roadway edge treatment is now complete.  This section is slightly more than 500’ long and was the most laborious part of the project, and will help prevent the undermining of the road in future major storm events.
  • Currently under construction is the drainage swale adjacent to the road, which will be Improved and Fortified.
  • Paving is the final step, which the contractor expects will begin the week of June 20th.

Barring any extreme weather that could impact progress of the project, the Engineer estimates that we might be able to open the road in 2-weeks (week of June 27th).

 The Morris County Park Commission Greatly Appreciates the Patience of Kinnelon Residents during these Emergency Road Repairs and Looks Forward to the Reopening of the Main Entrance Road shortly.

Kinnelon Borough

http://www.kinnelonboro.org/cn/news/index.cfm?NID=54716&jump2=0

Email a link to this web page.
Simply fill out this form and click Send.
*Fields in Red are required.
*You must enter a valid email
*You must enter a valid email.